Construction of Ecco on Orange (an investment of Atlantic American Fortune Fund II) is moving along quickly.  The structured parking garage is now erected and installation of MEPs (Mecahnical, Electrical and Plumbing) is now in progress. 

Stairwells #2 and #3 are installed and poured and Elevator Shaft #2 is complete.  Stairwells #1 and #4 and Elevator #4 are near completion.  

Conduit is now being installed along Orange Avenue for the burial of the existing overhead power lines.  Onsite primary power conduit has been installed to the transformer pad locations.  

Pouring of the Residential Building SOG (Slab on Grade) is scheduled to occur in July with framing materials onsite at the end of the month.  

 

Atlantic American Fortune Fund II is now closed to new investors.  To hear about our current offerings, please contact us at info@atlanticamericanpartners.com.  

 




Securities Disclaimer

This website is for informational purposes only and does not constitute an offer or solicitation to sell shares or securities. Any such offer or solicitation will be made only by means of an investment's confidential Offering Memorandum and in accordance with the terms of all applicable securities and other laws. This website does not constitute or form part of, and should not be construed as, any offer for sale or subscription of, or any invitation to offer to buy or subscribe for, any securities, nor should it or any part of it form the basis of, or be relied on in any connection with, any contract or commitment whatsoever. EB5Projects.com LLC and its affiliates expressly disclaim any and all responsibility for any direct or consequential loss or damage of any kind whatsoever arising directly or indirectly from: (i) reliance on any information contained in the website, (ii) any error, omission or inaccuracy in any such information or (iii) any action resulting therefrom.