The Northern Nevada economy continues to see impressive growth. Construction starts are increasing in efforts to meet the new demand for residential and commercial properties; thus, causing more worker shortages. While the Nevada State EB-5 Regional Centers sponsored project has been continuously manned, its completion has been somewhat delayed. Given the time delay, the project has adjusted its timeline for completion to early Summer of 2018.

Importantly tenants’ leases have not been impacted and will commence in the Spring of 2018. Further, the extension in completion time benefits H1-B Visa holders and immigrant investors by providing additional time to participate in this project and reap the benefits of the EB-5 Regional Program for permanent U.S. citizenship.

Project Update: January 5, 2018

Building A – Main Building 3-Story mixed use building. This building is anticipated to be completed by late first quarter of 2018.

Present Status:

1. Exterior framing is completed.
2. Roofing and interior waterproofing is completed.
3. Exterior windows and doors installed.
4. Exterior siding and trim details are in process.
5. Interior rough construction is also underway.

The work on Building A will continue through the winter as the building is weathered in.

  • The First Foor (Retail): An agreement with a family style restaurant has been made. The establishment will take up approximately 60% of the bottom floor. The tenant improvement plans are in process. Occupancy is estimated for no later than June 2018, depending on workforce availability.
  • The Second Floor (Office): The second floor is approximately 80% leased. Tenant improvements are underway. Occupancy is estimated for no later than May 2018, depending on workforce availability.
  • The Third Floor (Apartments): The 8 top floor apartments are rough framed. Currently, 16 parties are on the waitlist. In approximately 30 to 45 days, the tenants will be selected, assigned a unit and allowed to do minor customizations. Occupancy is estimated for April.

Building B – This building is comprised of two stand-alone apartments with garages. It is complete except for a few minor items and will be ready for leasing within the next 30 days.

Building C – Garages for apartments. This building is complete except for minor items.

If you are an immigrant investor interested in this exceptional project, please contact NVEB-5. NVEB-5 will provide you with information about participation in the EB-5 Immigrant Investor Program and help direct you to the project owner for more details about the NVEB-5 sponsored project.


http://nveb5.org/visa/sponsored-project-update-january-2018/

Mentions

States

  • Nevada


Securities Disclaimer

This website is for informational purposes only and does not constitute an offer or solicitation to sell shares or securities. Any such offer or solicitation will be made only by means of an investment's confidential Offering Memorandum and in accordance with the terms of all applicable securities and other laws. This website does not constitute or form part of, and should not be construed as, any offer for sale or subscription of, or any invitation to offer to buy or subscribe for, any securities, nor should it or any part of it form the basis of, or be relied on in any connection with, any contract or commitment whatsoever. EB5Projects.com LLC and its affiliates expressly disclaim any and all responsibility for any direct or consequential loss or damage of any kind whatsoever arising directly or indirectly from: (i) reliance on any information contained in the website, (ii) any error, omission or inaccuracy in any such information or (iii) any action resulting therefrom.